Skip to main content
ADA VIEW RESET
Work With Us

Project Status

A wide-ranging effort is underway to enhance infrastructure at Blount Island and Talleyrand terminals, with upgrades to wharves, on-dock rail, cranes and terminal pavement areas under construction. These capital improvements – made possible by federal and state funds – will enable JAXPORT to build the port of the future.


Blount Island Marine Terminal

Tenant Pavement Improvements - Phase II

Construction notice to proceed: March 29, 2017
Contract completion date: Sept. 15, 2017

Scope of the project is to construct a 6.14 acre parking facility for auto processing.

The project will be inclusive of yet not limited to:

  • Clearing and grubbing existing lot
  • Installation of storm drainage pipes, structures and outfalls
  • Construction of drainage pond
  • New perimeter fence

Vendors:

  • HDR, Inc. provided design services and is providing services during construction
  • Pars Construction Services, LLC is the contractor


Talleyrand Marine Terminal

Berth 7 & 8 Bulkhead Rehabilitation

Construction Notice to Proceed: October 31, 2016
Contract Completion Date: June 10, 2018

Scope of the project is to install a new steel sheet pile bulkhead at Berth 7 & 8. The total length of the wharf to be repaired is 1,780 lineal feet. The project is subdivided in three phases.

The project will be inclusive of yet not limited to:

  • Demolition of existing wharf structure to expose existing sheet pile wall
  • Installation of new steel sheet pile landside of existing sheet pile wall
  • Construction of new concrete cap on new sheet pile wall
  • Backfill trench
  • Reconstruct concrete relieving platform 
  • Installation of cathodic protection on new sheet pile
  • Construction of 3 storm water outfalls
  • Re-install ballast
  • Install lime rock and asphalt

Vendors:

  • HDR, Inc. provided design services and is providing services during construction
  • Hal Jones Contractor, Inc. is the contractor


Talleyrand Marine Terminal

Talleyrand North Gate Improvements

Construction Notice to Proceed: Jan. 11, 2017
Contract Completion Date: June 12, 2017

Scope of the project is to expand the northern entrance to the Talleyrand Marine Terminal in order to meet future demands for operations at this location.

Project is completed and ready for operation.

The project is inclusive of yet not limited to:

  • Demolition of existing asphalt at entrance to widen the entrance on Talleyrand Ave
  • Re-grading new lanes for better access off Talleyrand Avenue
  • Installation of a new canopy to cover 2 new lanes/booths
  • Installation of 5 new booths for all lanes
  • Modifications to employee parking lot
  • New fence and gates
  • New lime rock base, asphalt paving and striping
  • New gate arms at the Security plaza
  • New gate arms at the Interchange Building
  • New lighting

Vendors:

  • RS&H, Inc. was the design engineer
  • Pars Construction Services, LLC is the contractor